The Lebanon City Council on Monday night, was asked to approve an amendment to the engineering agreement for the Wastewater Treatment Plant phase 2 improvements. Public Works Director Richard Shockley said the agreement with Lamp, Rynearson and Associates will update the plan from 2015 which was sent to DNR.



right-click to download mp3

   

Shockley said what will be brought forward will be tied to some financing for the project as well. The bill approving phase 2 will require two readings by City Council. The Budgeted amount for the project is approximately $4-million-dollars.